TrafficTop story
Kapiolani Boulevard's $9.9 million rebuild starts Monday, Nov. 16, and will last about 18 months
The Kapiolani rebuild will cost $9.9 million and take about 18 months
- $9.9 million
- contract awarded to Hiilawe Construction LLC
- 18 months
- expected length of the project
- At least 1
- lane stays open in each direction
Sources: KHON2, Honolulu Star-Advertiser, hawaiinewsnow.com
If you drive Kapiolani Boulevard between Ward Avenue and Atkinson Drive, expect company. The city says the rebuild starts Monday, Nov. 16, and the $9.9 million contract went to Hiilawe Construction LLC.
It's more than patching potholes, said city design and construction director Haku Milles: "This is building a brand new road." Crews will start on the Ward side, trying to avoid the congestion around Ala Moana as best they can. Some shop owners say they only just heard about it. "It's going to hurt, definitely," said ProAm Golf Shop owner Nathan Yoshioka, who worries about the Christmas season.
- Work: new asphalt, curbs, gutters, sidewalks and traffic signals
- Also: striping and signs updated, trees trimmed
- Night work: possible in later phases
Kapiolani crews will work weekdays from 8:30 a.m. to 3:30 p.m.
Kapiolani Boulevard between Ward Avenue and Atkinson Drive
- 8:30 a.m. to 3:30 p.m.Weekday work, except holidays
- Starts
- Mon., Nov. 16
- Between
- Ward Ave. and Atkinson Dr.
Sources: KHON2, Honolulu Star-Advertiser, hawaiinewsnow.com
View as table
| When | What |
|---|---|
| 8:30 a.m. to 3:30 p.m. | Weekday work, except holidays |
| Starts | Mon., Nov. 16 |
| Between | Ward Ave. and Atkinson Dr. |
We suggest leaving extra time and following the posted signs and special-duty police officers in the work zone. Questions go to the Department of Design and Construction at 808-768-8400.